If you are a member of the site please login.
 

Sub-project Implementation

Reports / Annual (2005) / Province (02, BAT)

Distrinct
[ #valid contract ]
# Communes # Signed # Abandon Implementation Completed
0 % 30 % 50 % 80 % 90 % 100 %
201, Banan [ 13 ] 8 13 0 0 0 0 0 0 0 13
202, Thma Koul [ 13 ] 10 13 0 0 0 0 0 0 0 13
203, Battambang [ 15 ] 10 15 0 0 0 0 0 0 0 15
204, Bavel [ 11 ] 6 11 0 0 0 0 0 0 0 11
205, Aek Phnum [ 7 ] 7 7 0 0 0 0 0 0 0 7
206, Moung Ruessei [ 10 ] 11 11 1 0 0 0 0 0 0 10
207, Rotonak Mondol [ 5 ] 4 5 0 0 0 0 0 0 0 5
208, Sangkae [ 11 ] 10 11 0 0 0 0 0 0 0 11
209, Samlout [ 5 ] 7 5 0 0 0 0 0 0 0 5
210, Sampov Lun [ 6 ] 6 6 0 0 0 0 0 0 0 6
211, Phnum Proek [ 6 ] 5 6 0 0 0 0 0 0 0 6
212, Kamrieng [ 7 ] 6 7 0 0 0 0 0 0 0 7
213, Koas Krala [ 7 ] 6 7 0 0 0 0 0 0 0 7
Total [ 116 ] : 96 117 1 0 0 0 0 0 0 116

# valid contract = [ # signed ] - [ # abandon ]

Back to annual (2005).