Bidding Summary Report
Location: Kampong Chhnang \ Kampong Leaeng Budget Year: 2005
| Commune | Contract ID | Bid Date | # Of Bidders | # Valid Bidders | Qty Changed | Award To | Contract Value | Bidding Detail | |||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Name | Bid Value | Rejected | Note | ||||||||
| District: [404] Kampong Leaeng | |||||||||||
| Svay Rumpear | 040408/05/01 | 18-May-2005 | 4 | 4 | No | You Nan [ Khiev Sophany ] | 24,508,000 | Lun Sokhun [ Lun Sokhun ] | 23,920,200 | No | |
# Of Bidders: number of contractor submit their bid for the specific contract.
# Valid Bidders: number of contractor accepted by the bidding committee.
Rejected: Yes if the bidding committee reject contractor bidding request.