Bidding Summary Report

Location: Kampong Speu \ Samraong Tong Budget Year: 2005

Basedth    Chbar Mon    Kong Pisei    Aoral    Odongk    Phnum Sruoch    Samraong Tong    Thpong   

Commune Contract ID Bid Date # Of Bidders # Valid Bidders Qty Changed Award To Contract Value Bidding Detail
Name Bid Value Rejected Note
District: [507] Samraong Tong
Roleang Chak 050701/05/01 22-Jun-2005 4 4 No Theam Sao [ Theam Sao ] 17,955,000 Theam Sao [ Theam Sao ] 7,230,000 No
Nam Srun Construction Enterprise [ Nam Srun ] 7,600,000 No
Seng Chhun Heng [ Seng Chhun Heng ] 8,000,000 No
Building and construction company brak ry [ Prak ry ] 17,000,000 No
Roleang Chak 050701/05/02 22-Jun-2005 4 4 Yes Theam Sao [ Theam Sao ] 9,830,000 Theam Sao [ Theam Sao ] 17,955,000 No
Nam Srun Construction Enterprise [ Nam Srun ] 19,500,000 No
Seng Chhun Heng [ Seng Chhun Heng ] 19,900,000 No
Chiem Ty Company [ Chiem Ty ] 19,950,000 No
Kahaeng 050702/05/01 15-Feb-2004 7 7 No Chiem Ty Company [ Chiem Ty ] 27,909,900 Chiem Ty Company [ Chiem Ty ] 26,075,000 No
Nam Srun Construction Enterprise [ Nam Srun ] 26,433,000 No
Building and construction company brak ry [ Prak ry ] 27,757,000 No
Khtum Krang 050703/05/01 09-May-2005 6 6 No Chiem Ty Company [ Chiem Ty ] 31,716,000 Building and construction company brak ry [ Prak ry ] 3,184,500 No
Roleang Kreul 050706/05/01 22-Jun-2005 5 5 Yes Nam Srun Construction Enterprise [ Nam Srun ] 42,149,400 Chiem Ty Company [ Chiem Ty ] 31,597,000 No
Nam Srun Construction Enterprise [ Nam Srun ] 33,699,400 No
Aot Thy [ Aot Thy ] 37,074,137 No
Seng Chhun Heng [ Seng Chhun Heng ] 37,915,400 No
Building and construction company brak ry [ Prak ry ] 38,425,500 No
Skuh 050710/05/01 22-Jun-2005 7 7 Yes Chiem Ty Company [ Chiem Ty ] 37,278,300 Chiem Ty Company [ Chiem Ty ] 29,103,000 No
Nam Srun Construction Enterprise [ Nam Srun ] 29,849,500 No
Building and construction company brak ry [ Prak ry ] 31,000,000 No
Theam Sao [ Theam Sao ] 31,999,000 No
Aot Thy [ Aot Thy ] 32,834,559 No
Suong Bora Import Export and construction [ Suong Bora ] 33,400,000 No
Tan Muy [ Tan Simorn ] 36,508,000 No
Trapeang Kong 050713/05/01 22-Jun-2005 4 4 Yes Nam Srun Construction Enterprise [ Nam Srun ] 44,460,400 Nam Srun Construction Enterprise [ Nam Srun ] 37,800,000 No
Theam Sao [ Theam Sao ] 38,312,000 No
Aot Thy [ Aot Thy ] 39,137,736 No
Tan Muy [ Tan Simorn ] 40,102,000 No
Tumpoar Meas 050714/05/01 22-Jun-2005 6 6 Yes Chiem Ty Company [ Chiem Ty ] 32,003,600 Chiem Ty Company [ Chiem Ty ] 25,622,000 No
Nam Srun Construction Enterprise [ Nam Srun ] 25,892,000 No
Aot Thy [ Aot Thy ] 28,027,700 No
Suong Bora Import Export and construction [ Suong Bora ] 28,800,000 No
Building and construction company brak ry [ Prak ry ] 28,800,000 No
Tan Muy [ Tan Simorn ] 30,680,000 No
Voa Sa 050715/05/01 22-Jun-2005 7 7 Yes Nam Srun Construction Enterprise [ Nam Srun ] 32,711,000 Nam Srun Construction Enterprise [ Nam Srun ] 27,776,600 No
Chiem Ty Company [ Chiem Ty ] 27,812,000 No
Aot Thy [ Aot Thy ] 28,794,568 No
Tan Muy [ Tan Simorn ] 29,448,900 No
Koyoen Svayprovoat [ Pang Sokhom ] 29,448,900 No
Building and construction company brak ry [ Prak ry ] 29,722,000 No
Suong Bora Import Export and construction [ Suong Bora ] 30,802,800 No

# Of Bidders: number of contractor submit their bid for the specific contract.
# Valid Bidders: number of contractor accepted by the bidding committee.
Rejected: Yes if the bidding committee reject contractor bidding request.