Bidding Summary Report

Location: Banteay Meanchey \ Preah Netr Preah Budget Year: 2006

Mongkol Borei    Phnum Srok    Preah Netr Preah    Ou Chrov    Serei Saophoan    Thma Puok    Svay Chek    Malai   

Commune Contract ID Bid Date # Of Bidders # Valid Bidders Qty Changed Award To Contract Value Bidding Detail
Name Bid Value Rejected Note
District: [104] Preah Netr Preah
Chob Veari 010402/06/01 03-May-2006 4 4 Yes Tang Samnang [ Chao Yinh ] 29,632,113 Tang Samnang [ Chao Yinh ] 32,907,951 No The bid price lower than other
Tang Thai Kheang [ Tang BunKheang ] 33,204,380 No
Tes Kheng [ Tes Kheng ] 33,500,874 No
I Danit [ I Danit ] 34,100,000 No
Chob Veari 010402/06/02 03-May-2006 3 3 No KC contruction (Kim Cheang) [ Kim Cheang ] 6,014,002 KC contruction (Kim Cheang) [ Kim Cheang ] 6,014,000 No The bid price lower than other
Prasat 010404/06/01 26-Jun-2006 3 3 Yes Tang Samnang [ Chao Yinh ] 30,707,368 Tang Samnang [ Chao Yinh ] 28,515,560 No The bid price lower than other
I Danit [ I Danit ] 28,587,000 No
Tes Kheng [ Tes Kheng ] 29,130,000 No
Preah Netr Preah 010405/06/01 22-Apr-2006 4 4 No Brok Toeung [ Brok Toeung ] 39,549,597 Brok Toeung [ Brok Toeung ] 38,952,147 No The bid price lower than other
Seng Kheng [ Seng Kheng ] 39,347,500 No
Uk Sieb [ Uk Sieb ] 39,426,691 No
KC contruction (Kim Cheang) [ Kim Cheang ] 39,545,326 No

# Of Bidders: number of contractor submit their bid for the specific contract.
# Valid Bidders: number of contractor accepted by the bidding committee.
Rejected: Yes if the bidding committee reject contractor bidding request.