Bidding Summary Report
Location: Mondul Kiri \ Ou Reang Budget Year: 2008
| Commune | Contract ID | Bid Date | # Of Bidders | # Valid Bidders | Qty Changed | Award To | Contract Value | Bidding Detail | |||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Name | Bid Value | Rejected | Note | ||||||||
| District: [1103] Ou Reang | |||||||||||
| Dak Dam | 110301/08/02 | 08-Jan-2009 | 2 | 2 | No | Mr khouv Phaly [ Mr khouv Phaly ] | 76,455,000 | Mr khouv Phaly [ Mr khouv Phaly ] | 76,355,000 | No | |
| Mr Khouv Meng [ Mr Khouv Meng ] | 76,358,000 | No | |||||||||
# Of Bidders: number of contractor submit their bid for the specific contract.
# Valid Bidders: number of contractor accepted by the bidding committee.
Rejected: Yes if the bidding committee reject contractor bidding request.