Bidding Summary Report
Location: Prey Veng \ Kampong Leav Budget Year: 2008
| Commune | Contract ID | Bid Date | # Of Bidders | # Valid Bidders | Qty Changed | Award To | Contract Value | Bidding Detail | |||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Name | Bid Value | Rejected | Note | ||||||||
| District: [1411] Kampong Leav | |||||||||||
| Baray | 141101/08/01 | 08-Aug-2008 | 6 | 4 | Yes | Tiv Navuth [ Tiv Navuth ] | 32,145,000 | Tiv Navuth [ Tiv Navuth ] | 34,525,000 | No | Lowest price Reduce output |
| Heang Lun [ Heang Lun ] | 35,393,900 | Yes | invalide wrong calculation | ||||||||
| Heng Ravuth [ Heng Ravuth ] | 36,850,000 | No | |||||||||
| Ok Meng Leng [ Ok Meng Leng ] | 37,262,500 | No | |||||||||
| Chan Uok [ Chan Uok ] | 43,875,000 | No | |||||||||
| Chreng Ray [ Chreng Ray ] | 54,260,000 | Yes | invalide ( wrong bid form ) | ||||||||
| Cheung Tuek | 141102/08/02 | 10-Apr-2008 | 3 | 3 | Yes | Chreng Ray [ Chreng Ray ] | 31,927,500 | Chreng Ray [ Chreng Ray ] | 28,341,300 | No | Lowest price ( negotiation to expand output ) |
| Ly Bunchhay [ Ly Bunchhay ] | 32,955,000 | No | |||||||||
| Chhun Yeang [ Chhun Yeang ] | 32,955,000 | No | |||||||||
| Kampong Leav | 141103/08/02 | 08-Aug-2008 | 4 | 3 | Yes | Heng Ravuth [ Heng Ravuth ] | 46,609,000 | Heng Ravuth [ Heng Ravuth ] | 50,410,000 | No | Lowest price Reduce output |
| Ok Meng Leng [ Ok Meng Leng ] | 54,350,000 | Yes | invalide wrong calculation | ||||||||
| Chheng Eng Srunn [ Chheng Eng Srunn ] | 54,510,000 | No | |||||||||
| Um Chhan [ Um Chhan ] | 57,130,000 | No | |||||||||
| Pou Rieng | 141104/08/01 | 10-Apr-2008 | 4 | 4 | Yes | Prum yan [ Prum yan ] | 34,700,000 | Prum yan [ Prum yan ] | 20,450,000 | No | Lowest price ( negotiation to expand output ) |
| Pang Sroy [ Pang Sroy ] | 28,050,000 | No | |||||||||
| Ly Bunchhay [ Ly Bunchhay ] | 33,200,000 | No | |||||||||
| Chhun Yeang [ Chhun Yeang ] | 33,300,000 | No | |||||||||
| Ta Kao | 141108/08/01 | 27-May-2008 | 13 | 12 | Yes | Lu Hagn [ Lu Hagn ] | 42,909,700 | Lu Hagn [ Lu Hagn ] | 19,999,700 | No | Lowest price ( negotiation to expand output ) |
| Um Chhan [ Um Chhan ] | 23,501,000 | No | |||||||||
| Phon Vuthy [ Phon Vuthy ] | 24,760,000 | No | |||||||||
| Prak Eang [ Prak Eang ] | 25,760,000 | No | |||||||||
| Chheng Eng Srunn [ Chheng Eng Srunn ] | 27,830,000 | No | |||||||||
| Chan Uok [ Chan Uok ] | 28,386,600 | No | |||||||||
| Chan Bunna [ Chan Bunna ] | 30,000,000 | No | |||||||||
| Oeng Meng Heang [ Oeng Meng Heang ] | 33,872,000 | No | |||||||||
| Chea Saran [ Chea Saran ] | 33,875,000 | No | |||||||||
| Thoeun Sophoeun [ Thoeun Sophoeun ] | 35,298,200 | No | |||||||||
| Muon Mo [ Muon Mo ] | 36,839,000 | No | |||||||||
| Heong Horn [ Heong Horn ] | 36,919,000 | Yes | Invalide wrong calculation | ||||||||
| Kuy Rith [ Kuy Rith ] | 39,662,000 | No | |||||||||
# Of Bidders: number of contractor submit their bid for the specific contract.
# Valid Bidders: number of contractor accepted by the bidding committee.
Rejected: Yes if the bidding committee reject contractor bidding request.