Bidding Summary Report

Location: Takeo \ Kiri Vong Budget Year: 2008

Angkor Borei    Bati    Bourei Cholsar    Kiri Vong    Kaoh Andaet    Prey Kabbas    Samraong    Doun Kaev    Tram Kak    Treang   

Commune Contract ID Bid Date # Of Bidders # Valid Bidders Qty Changed Award To Contract Value Bidding Detail
Name Bid Value Rejected Note
District: [2104] Kiri Vong
Angk Prasat 210401/08/01 05-Jun-2008 4 4 Yes Heng Pong [ Heng Pong ] 34,644,200 Heng Pong [ Heng Pong ] 37,770,000 No Won Bidder
General construction [ Mam Davy ] 38,119,400 No -
Korng sophoeurn [ Korng Sophoeurn ] 38,200,000 No Bidding Attendance
Sin Koeun [ Sin Koeun ] 38,460,000 No -
Preah Bat Choan Chum 210402/08/01 05-Jun-2008 3 3 Yes Korng sophoeurn [ Korng Sophoeurn ] 53,285,500 Korng sophoeurn [ Korng Sophoeurn ] 48,768,000 No Won Bidder
General construction [ Mam Davy ] 49,242,000 No Bidding Attendance
Heng Pong [ Heng Pong ] 52,500,000 No -
Kamnab 210403/08/01 05-Jun-2008 3 3 Yes General construction [ Mam Davy ] 27,484,100 General construction [ Mam Davy ] 30,600,000 No Won Bidder
Heng Pong [ Heng Pong ] 31,710,000 No Bidding Attendance
Korng sophoeurn [ Korng Sophoeurn ] 32,300,000 No -
Kampeaeng 210404/08/01 02-Sep-2008 4 4 Yes Nu Sarun [ Nu Sarun ] 33,589,600 Nu Sarun [ Nu Sarun ] 39,500,000 No Won Bidder
Mom SamAn [ Mom SamAn ] 41,920,000 No Bidding Attendance
Chea Koy [ Chea Koy ] 43,000,000 No -
Dourng Sambo [ Dourng Sambo ] 43,500,000 No -
Kiri Chong Kaoh 210405/08/01 20-May-2008 5 5 Yes Local glorious [ Hean Phorn ] 31,243,700 Local glorious [ Hean Phorn ] 33,345,500 No Won Bidder
General construction [ Mam Davy ] 33,651,400 No Bidding Attendance
Koyont Svaybravatt [ Pang Sokhom ] 35,000,000 No -
Korng sophoeurn [ Korng Sophoeurn ] 36,000,000 No -
Parng Sochea [ Parng Sochea ] 36,700,000 No -
Kouk Prech 210406/08/01 20-May-2008 4 4 Yes Parng Sochea [ Parng Sochea ] 41,090,000 Parng Sochea [ Parng Sochea ] 45,690,000 No Won Bidder
Koyont Svaybravatt [ Pang Sokhom ] 46,000,000 No Bidding Attendance
Korng sophoeurn [ Korng Sophoeurn ] 48,872,000 No -
General construction [ Mam Davy ] 48,873,000 No -
Ream Andaeuk 210410/08/01 05-Jun-2008 4 4 Yes Sin Koeun [ Sin Koeun ] 31,333,300 Sin Koeun [ Sin Koeun ] 32,900,000 No Won Bidder
Heng Pong [ Heng Pong ] 33,000,000 No -
General construction [ Mam Davy ] 33,230,100 No -
Korng sophoeurn [ Korng Sophoeurn ] 33,300,000 No Bidding Attendance
Saom 210411/08/01 20-May-2008 6 6 Yes Local glorious [ Hean Phorn ] 35,980,900 Local glorious [ Hean Phorn ] 39,670,200 No Won Bidder
Koyont Svaybravatt [ Pang Sokhom ] 40,700,000 No -
Korng sophoeurn [ Korng Sophoeurn ] 41,650,000 No -
Parng Sochea [ Parng Sochea ] 42,800,000 No -
General construction [ Mam Davy ] 43,180,800 No Bidding Attendance
Mom SamAn [ Mom SamAn ] 44,000,000 No -
Ta Ou 210412/08/01 20-May-2008 6 6 Yes Mom SamAn [ Mom SamAn ] 36,859,800 Mom SamAn [ Mom SamAn ] 40,000,000 No Won Bidder
Koyont Svaybravatt [ Pang Sokhom ] 40,800,000 No -
Local glorious [ Hean Phorn ] 41,124,400 No -
Korng sophoeurn [ Korng Sophoeurn ] 42,000,000 No Bidding Attendance
Parng Sochea [ Parng Sochea ] 42,998,000 No -
General construction [ Mam Davy ] 43,233,000 No -

# Of Bidders: number of contractor submit their bid for the specific contract.
# Valid Bidders: number of contractor accepted by the bidding committee.
Rejected: Yes if the bidding committee reject contractor bidding request.