Bidding Summary Report
Location: Kampot \ Kampot Budget Year: 2008
| Commune | Contract ID | Bid Date | # Of Bidders | # Valid Bidders | Qty Changed | Award To | Contract Value | Bidding Detail | |||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Name | Bid Value | Rejected | Note | ||||||||
| District: [707] Kampot | |||||||||||
| Prey Khmum | 070712/08/01 | 19-Sep-2008 | 4 | 4 | No | Monorom [ Meas khemra ] | 30,100,000 | khut chanda Struction [ Chheung Saoly ] | 29,500,000 | No | |
# Of Bidders: number of contractor submit their bid for the specific contract.
# Valid Bidders: number of contractor accepted by the bidding committee.
Rejected: Yes if the bidding committee reject contractor bidding request.