Contract Outputs

Location: Battambang \ Sangkae Budget Year: 2004

Banan    Thma Koul    Battambang    Bavel    Aek Phnum    Moung Ruessei    Rotonak Mondol    Sangkae    Samlout    Sampov Lun    Phnum Proek    Kamrieng    Koas Krala   

Sangkae, Anlong Vil

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 020801/04/01 TSO Oum Naram Project Type Rural Transport 36,361,000
Ou Muni Muoy 1 202 Laterite road 1.20 [ 1.20 ] Km 6,151,667 3.000 Width (m) 495.000 Earth fill m3 7,382,000
Anlong Vil 2 202 Laterite road 2.14 [ 2.84 ] Km 9,577,559 4.000 Width (m) 0.150 Earth fill m3 27,229,000
Svay Kang 4 211 Single pipe culvert 1.00 [ 1.00 ] Place 1,750,000 0.800 Diameter (m) 5.000 Length (m) 1,750,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  36,361,000

Sangkae, Norea

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 020802/04/01 TSO Oum Naram Project Type Rural Transport 14,309,800
Balat 1 202 Laterite road 1.40 [ 1.40 ] Km 7,141,243 3.000 Width (m) 150.000 Earth fill m3 9,962,034
Norea Pir 2 202 Laterite road 0.20 [ 0.61 ] Km 7,139,189 3.000 Width (m) 150.000 Earth fill m3 4,347,766
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  14,309,800
Contract ID 020802/04/02 TSO Oum Naram Project Type Rural Transport 7,400,000
Ta Kok 1 212 Double pipe culvert 1.00 [ 1.00 ] Place 2,207,500 0.800 Diameter (m) 5.000 Length (m) 2,207,500
Balat 2 211 Single pipe culvert 3.00 [ 3.00 ] Place 995,000 0.600 Diameter (m) 5.000 Length (m) 2,985,000
Norea Pir 3 212 Double pipe culvert 1.00 [ 1.00 ] Place 2,207,500 0.800 Diameter (m) 5.000 Length (m) 2,207,500
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  7,400,000

Sangkae, Ta Pon

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 020803/04/01 TSO Oum Naram Project Type Rural Transport 31,324,400
Ta Pon 1 202 Laterite road 1.26 [ 1.36 ] Km 8,809,412 3.000 Width (m) 150.000 Earth fill m3 11,980,800
Ta Pon 4 211 Single pipe culvert 1.00 [ 1.00 ] Place 1,700,000 0.800 Diameter (m) 5.000 Length (m) 1,700,000
Basaet 5 202 Laterite road 1.05 [ 1.38 ] Km 8,808,289 3.000 Width (m) 150.000 Earth fill m3 12,155,439
Samdach 6 202 Laterite road 0.60 [ 0.62 ] Km 8,809,360 3.000 Width (m) 150.000 Earth fill m3 5,488,231
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  31,324,470

Sangkae, Roka

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 020804/04/01 TSO Oum Naram Project Type Rural Transport 25,367,800
Chhung Tradak 1 202 Laterite road 1.96 [ 1.96 ] Km 8,181,276 3.000 Width (m) 150.000 Earth fill m3 16,035,300
Pou Batdambang 2 202 Laterite road 0.54 [ 1.01 ] Km 8,182,546 3.000 Width (m) 150.000 Earth fill m3 8,272,554
Chhung Tradak 3 211 Single pipe culvert 1.00 [ 1.00 ] Place 1,060,000 0.600 Diameter (m) 8.000 Length (m) 1,060,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  25,367,854

Sangkae, Kampong Preah

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 020805/04/01 TSO Oum Naram Project Type Rural Transport 26,340,200
Srah Kaev 1 202 Laterite road 2.55 [ 2.85 ] Km 8,914,105 3.000 Width (m) 150.000 Earth fill m3 25,405,200
Kampong Preah 2 211 Single pipe culvert 1.00 [ 1.00 ] Place 935,000 0.600 Diameter (m) 5.000 Length (m) 935,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  26,340,200

Sangkae, Kampong Preang

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 020806/04/01 TSO Oum Naram Project Type Rural Transport 26,905,700
Kbal Thnal 1 202 Laterite road 0.30 [ 0.30 ] Km 9,800,000 3.000 Width (m) 150.000 Earth fill m3 2,940,000
Thmei 2 202 Laterite road 1.45 [ 1.45 ] Km 9,772,966 3.000 Width (m) 150.000 Earth fill m3 14,170,800
Sambok Ak 3 202 Laterite road 0.63 [ 1.00 ] Km 9,834,237 3.000 Width (m) 0.150 Earth fill m3 9,794,900
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  26,905,700

Sangkae, Reang Kesei

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 020807/04/01 TSO Oum Naram Project Type Rural Transport 24,505,700
Voat Kandal 1 202 Laterite road 1.35 [ 1.35 ] Km 9,936,985 3.000 Width (m) 150.000 Earth fill m3 13,414,930
Svay Cheat 2 202 Laterite road 0.71 [ 1.12 ] Km 9,929,069 3.000 Width (m) 0.150 Earth fill m3 11,090,770
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  24,505,700

Sangkae, Ou Dambang Muoy

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 020808/04/01 TSO Oum Naram Project Type Rural Transport 32,192,600
Samraong Kaong 1 202 Laterite road 1.20 [ 1.20 ] Km 8,252,250 3.000 Width (m) 150.000 Earth fill m3 9,902,700
Ou Sralau 2 202 Laterite road 1.49 [ 1.49 ] Km 8,252,253 3.000 Width (m) 150.000 Earth fill m3 12,271,100
Voat Chaeng 3 202 Laterite road 0.26 [ 0.90 ] Km 8,252,280 3.000 Width (m) 150.000 Earth fill m3 7,418,800
Ou Sralau 4 211 Single pipe culvert 1.00 [ 1.00 ] Place 1,000,000 0.600 Diameter (m) 5.000 Length (m) 1,000,000
Samraong Kaong 5 211 Single pipe culvert 1.00 [ 1.00 ] Place 1,600,000 0.800 Diameter (m) 5.000 Length (m) 1,600,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  32,192,600

Sangkae, Ou Dambang Pir

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 020809/04/01 TSO Oum Naram Project Type Rural Transport 29,486,800
Tuol Lvieng 1 201 Earth road 2.35 [ 2.82 ] Km 9,469,642 4.000 Width (m) 500.000 Earth fill m3 26,732,800
Tuol Lvieng 2 211 Single pipe culvert 3.00 [ 3.00 ] Place 918,000 0.600 Diameter (m) 5.000 Length (m) 2,754,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  29,486,800

Sangkae, Voat Ta Muem

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 020810/04/01 TSO Oum Naram Project Type Rural Transport 18,965,400
Kampong Chlang 1 202 Laterite road 1.50 [ 1.54 ] Km 7,908,523 3.000 Width (m) 150.000 Earth fill m3 12,155,400
Ou Sralau 2 211 Single pipe culvert 1.00 [ 1.00 ] Place 1,700,000 0.800 Diameter (m) 5.000 Length (m) 1,700,000
Kampong Chlang 3 211 Single pipe culvert 1.00 [ 1.00 ] Place 1,022,000 0.600 Diameter (m) 5.000 Length (m) 1,022,000
Kampong Ampil 4 211 Single pipe culvert 1.00 [ 1.00 ] Place 1,022,000 0.600 Diameter (m) 5.000 Length (m) 1,022,000
Ou Khcheay 5 211 Single pipe culvert 1.00 [ 2.00 ] Place 1,022,000 0.600 Diameter (m) 5.000 Length (m) 2,044,000
Sla Kram 6 211 Single pipe culvert 1.00 [ 1.00 ] Place 1,022,000 0.600 Diameter (m) 5.000 Length (m) 1,022,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  18,965,400
Contract ID 020810/04/02 TSO Oum Naram Project Type Irrigation 14,995,700
Kampong Chlang 1 452 Single pipe Culvert with gate 3.00 [ 3.00 ] Place 2,133,500 0.600 Diameter (m) 3.000 Width (m) 6,400,500
Kampong Chlang 2 452 Single pipe Culvert with gate 2.00 [ 2.00 ] Place 2,341,500 0.600 Diameter (m) 5.000 Width (m) 4,683,000
Kampong Chlang 3 452 Single pipe Culvert with gate 1.00 [ 1.00 ] Place 3,912,200 0.600 Diameter (m) 5.000 Width (m) 3,912,200
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  14,995,700