Contract Outputs
Location: Battambang \ Banan Budget Year: 2007
Banan
Thma Koul
Battambang
Bavel
Aek Phnum
Moung Ruessei
Rotonak Mondol
Sangkae
Samlout
Sampov Lun
Phnum Proek
Kamrieng
Koas Krala
Banan, Kantueu Muoy
| Village |
No. |
Code |
Description |
Qty [Contracted] |
Unit |
Dimension #1 |
Dimension #2 |
Total |
| Contract ID |
020101/07/01 |
TSO |
Sem Vanno |
Project Type |
Rural Domestic Water Supplies |
23,962,400 |
| Thmei |
1 |
141 |
Pond with no filter |
1.00 [ 1.00 ] |
Place |
11,981,200 |
3.000 Depth (m) |
2,484.000 Volume (m3) |
11,981,200 |
| Kampong Ampil |
2 |
141 |
Pond with no filter |
1.00 [ 1.00 ] |
Place |
11,981,200 |
3.000 Depth (m) |
2,484.000 Volume (m3) |
11,981,200 |
| Note: Qty [Contract] : Planned qty [ qty in contract signed ] |
Grand Total: |
23,962,400 |
Banan, Kantueu Pir
| Village |
No. |
Code |
Description |
Qty [Contracted] |
Unit |
Dimension #1 |
Dimension #2 |
Total |
| Contract ID |
020102/07/01 |
TSO |
Sem Vanno |
Project Type |
Rural Transport |
28,670,000 |
| Phnom Kul |
1 |
201 |
Earth road |
1.85 [ 3.85 ] |
Km |
7,226,541 |
4.000 Width (m) |
10,461.000 Earth fill m3 |
27,833,023 |
| Phnom Kul |
2 |
211 |
Single pipe culvert |
1.00 [ 1.00 ] |
Place |
836,967 |
0.600 Diameter (m) |
5.000 Length (m) |
836,967 |
| Note: Qty [Contract] : Planned qty [ qty in contract signed ] |
Grand Total: |
28,669,990 |
Banan, Bay Damram
| Village |
No. |
Code |
Description |
Qty [Contracted] |
Unit |
Dimension #1 |
Dimension #2 |
Total |
| Contract ID |
020103/07/01 |
TSO |
Sem Vanno |
Project Type |
Rural Transport |
30,372,000 |
| Tuol Chranieng |
1 |
201 |
Earth road |
1.96 [ 3.95 ] |
Km |
7,690,087 |
4.000 Width (m) |
8,373.000 Earth fill m3 |
30,371,999 |
| Note: Qty [Contract] : Planned qty [ qty in contract signed ] |
Grand Total: |
30,371,999 |
Banan, Chheu Teal
| Village |
No. |
Code |
Description |
Qty [Contracted] |
Unit |
Dimension #1 |
Dimension #2 |
Total |
| Contract ID |
020104/07/01 |
TSO |
Sem Vanno |
Project Type |
Rural Transport |
40,954,700 |
| Svay Prakeab |
1 |
202 |
Laterite road |
1.79 [ 2.87 ] |
Km |
14,259,500 |
3.000 Width (m) |
1,113.480 Earth fill m3 |
40,954,710 |
| Note: Qty [Contract] : Planned qty [ qty in contract signed ] |
Grand Total: |
40,954,710 |
Banan, Chaeng Mean Chey
| Village |
No. |
Code |
Description |
Qty [Contracted] |
Unit |
Dimension #1 |
Dimension #2 |
Total |
| Contract ID |
020105/07/01 |
TSO |
Sem Vanno |
Project Type |
Rural Transport |
25,997,200 |
| Changhour Svay |
1 |
201 |
Earth road |
1.10 [ 1.77 ] |
Km |
12,412,640 |
4.000 Width (m) |
3,422.000 Earth fill m3 |
21,970,373 |
| Changhour Svay |
2 |
211 |
Single pipe culvert |
2.00 [ 2.00 ] |
Place |
1,503,472 |
0.800 Diameter (m) |
5.000 Length (m) |
3,006,944 |
| Changhour Svay |
3 |
211 |
Single pipe culvert |
1.00 [ 1.00 ] |
Place |
1,019,889 |
0.600 Diameter (m) |
5.000 Length (m) |
1,019,889 |
| Note: Qty [Contract] : Planned qty [ qty in contract signed ] |
Grand Total: |
25,997,206 |
Banan, Phnum Sampov
| Village |
No. |
Code |
Description |
Qty [Contracted] |
Unit |
Dimension #1 |
Dimension #2 |
Total |
| Contract ID |
020106/07/01 |
TSO |
Sem Vanno |
Project Type |
Rural Transport |
39,026,300 |
| Sampov Kaeut |
1 |
202 |
Laterite road |
2.71 [ 2,870.40 ] |
Km |
13,596 |
3.000 Width (m) |
165.750 Earth fill m3 |
39,026,303 |
| Note: Qty [Contract] : Planned qty [ qty in contract signed ] |
Grand Total: |
39,026,303 |
Banan, Snoeng
| Village |
No. |
Code |
Description |
Qty [Contracted] |
Unit |
Dimension #1 |
Dimension #2 |
Total |
| Contract ID |
020107/07/01 |
TSO |
Sem Vanno |
Project Type |
Rural Transport |
42,470,500 |
| Snoeng Lech |
1 |
202 |
Laterite road |
1.33 [ 1.33 ] |
Km |
14,300,000 |
3.000 Width (m) |
0.000 Earth fill m3 |
19,076,200 |
| Boeng Prei |
2 |
202 |
Laterite road |
1.09 [ 1,199.60 ] |
Km |
16,001 |
3.000 Width (m) |
0.000 Earth fill m3 |
19,194,296 |
| Boeng Prei |
3 |
211 |
Single pipe culvert |
1.00 [ 1.00 ] |
Place |
4,200,000 |
1.000 Diameter (m) |
5.000 Length (m) |
4,200,000 |
| Note: Qty [Contract] : Planned qty [ qty in contract signed ] |
Grand Total: |
42,470,496 |
Banan, Ta Kream
| Village |
No. |
Code |
Description |
Qty [Contracted] |
Unit |
Dimension #1 |
Dimension #2 |
Total |
| Contract ID |
020108/07/01 |
TSO |
Sem Vanno |
Project Type |
Rural Transport |
48,289,500 |
| Thmei |
1 |
201 |
Earth road |
2.54 [ 5.45 ] |
Km |
8,385,441 |
4.000 Width (m) |
8,498.000 Earth fill m3 |
45,700,653 |
| Thmei |
2 |
211 |
Single pipe culvert |
3.00 [ 3.00 ] |
Place |
862,950 |
0.600 Diameter (m) |
5.000 Length (m) |
2,588,850 |
| Note: Qty [Contract] : Planned qty [ qty in contract signed ] |
Grand Total: |
48,289,503 |