Contract Outputs

Location: Preah Vihear \ Tbaeng Mean chey Budget Year: 2008

Chey Saen    Chhaeb    Choam Khsant    Kuleaen    Rovieng    Sangkom Thmei    Tbaeng Mean chey   

Tbaeng Mean chey, Kampong Pranak

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 130701/08/01 TSO Sieng Mao Project Type Rural Transport 38,160,600
Srah Chhuk 1 202 Laterite road 0.36 [ 0.49 ] Km 33,771,620 4.500 Width (m) 550.000 Earth fill m3 16,548,094
Srah Chhuk 2 211 Single pipe culvert 1.00 [ 1.00 ] Place 2,756,883 0.600 Diameter (m) 6.000 Length (m) 2,756,883
Srah Chhuk 3 211 Single pipe culvert 1.00 [ 1.00 ] Place 3,399,577 0.800 Diameter (m) 6.000 Length (m) 3,399,577
Kouk Beng 4 202 Laterite road 5.90 [ 0.76 ] Km 15,926,650 4.500 Width (m) 754.000 Earth fill m3 12,056,474
Kouk Beng 5 211 Single pipe culvert 1.00 [ 1.00 ] Place 3,399,577 0.800 Diameter (m) 6.000 Length (m) 3,399,577
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  38,160,605

Tbaeng Mean chey, Pal Hal

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 130702/08/01 TSO Sieng Mao Project Type Rural Transport 40,000,000
Pal Hal 1 202 Laterite road 1.30 [ 1.30 ] Km 30,769,230 5.000 Width (m) 150.000 Earth fill m3 39,999,999
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  39,999,999

Tbaeng Mean chey, Chhean Mukh

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 130703/08/01 TSO Sieng Mao Project Type Rural Transport 32,900,000
Bak Kam 1 202 Laterite road 0.61 [ 0.61 ] Km 40,732,230 4.500 Width (m) 453.750 Earth fill m3 24,642,999
Bak Kam 2 211 Single pipe culvert 3.00 [ 3.00 ] Place 2,752,333 0.600 Diameter (m) 6.000 Length (m) 8,256,999
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  32,899,998
Contract ID 130703/08/02 TSO Sieng Mao Project Type Rural Domestic Water Supplies 7,243,000
Moha Phal 1 121 Drilled well with VN no 6 pump 1.00 [ 1.00 ] Place 3,621,500 30.000 Depth (m) 100.000 Diameter (mm) 3,621,500
Sedthkakech 2 121 Drilled well with VN no 6 pump 1.00 [ 1.00 ] Place 3,621,500 30.000 Depth (m) 100.000 Diameter (mm) 3,621,500
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  7,243,000

Tbaeng Mean chey, Pou

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 130704/08/01 TSO Sieng Mao Project Type Rural Transport 62,000,000
Pou 1 202 Laterite road 1.44 [ 1.44 ] Km 38,401,260 4.500 Width (m) 4,415.000 Earth fill m3 55,105,808
Pou 2 212 Double pipe culvert 1.00 [ 1.00 ] Place 4,256,273 0.600 Diameter (m) 6.000 Length (m) 4,256,273
Pou 3 211 Single pipe culvert 1.00 [ 1.00 ] Place 2,637,918 0.600 Diameter (m) 6.000 Length (m) 2,637,918
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  61,999,999

Tbaeng Mean chey, Prame

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 130705/08/01 TSO Sieng Mao Project Type Rural Transport 26,700,000
Srae Prang 1 202 Laterite road 0.68 [ 0.68 ] Km 39,207,050 4.500 Width (m) 2,003.000 Earth fill m3 26,700,001
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  26,700,001

Tbaeng Mean chey, Preah Khleang

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 130706/08/01 TSO Sieng Mao Project Type Rural Transport 63,580,000
Anlong Svay 1 202 Laterite road 1.20 [ 1.24 ] Km 39,640,000 4.000 Width (m) 3,127.000 Earth fill m3 49,153,600
Anlong Svay 2 211 Single pipe culvert 5.00 [ 4.00 ] Place 2,756,850 0.600 Diameter (m) 6.000 Length (m) 11,027,400
Anlong Svay 3 211 Single pipe culvert 1.00 [ 1.00 ] Place 3,399,000 0.800 Diameter (m) 6.000 Length (m) 3,399,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  63,580,000