Contract Outputs

Location: Kampong Thom \ Baray Budget Year: 2008

Baray    Kampong Svay    Stueng Saen    Prasat Balangk    Prasat Sambour    Sandan    Santuk    Stoung   

Baray, Bak Sna

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060101/08/01 TSO Chhear Nimol Project Type Rural Transport 34,111,400
Trapeang Tuk 1 202 Laterite road 0.88 [ 0.77 ] Km 41,206,880 4.000 Width (m) 3,339.000 Earth fill m3 31,877,642
Trapeang Tuk 2 211 Single pipe culvert 1.00 [ 1.00 ] Place 2,233,758 0.600 Diameter (m) 5.000 Length (m) 2,233,758
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  34,111,400

Baray, Ballangk

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060102/08/01 TSO Chhear Nimol Project Type Rural Transport 48,975,800
Doung 1 202 Laterite road 0.81 [ 0.72 ] Km 63,315,000 4.000 Width (m) 4,430.000 Earth fill m3 45,840,060
Doung 2 211 Single pipe culvert 1.00 [ 1.00 ] Place 3,135,828 0.800 Diameter (m) 5.000 Length (m) 3,135,828
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  48,975,888

Baray, Baray

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060103/08/01 TSO Eung Socheat Project Type Irrigation 43,614,700
Svay 1 420 Canal 1.40 [ 1.40 ] Km 19,087,429 0.600 Depth (m) 3,920.000 Volume (m3) 26,722,401
Chakto Louk 2 420 Canal 1.15 [ 0.87 ] Km 19,371,940 0.600 Depth (m) 3,887.000 Volume (m3) 16,892,332
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  43,614,732

Baray, Boeng

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060104/08/01 TSO Eung Socheat Project Type Rural Transport 38,659,900
Boeng Khang Cheung 1 202 Laterite road 1.28 [ 1.14 ] Km 33,971,870 4.000 Width (m) 1,940.000 Earth fill m3 38,659,988
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  38,659,988

Baray, Chaeung Daeung

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060105/08/01 TSO Chhear Nimol Project Type Rural Transport 41,379,300
Prey Dom 1 201 Earth road 1.00 [ 1.00 ] Km 41,379,398 4.000 Width (m) 2,614.000 Earth fill m3 41,379,398
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  41,379,398

Baray, Chranieng

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060106/08/01 TSO Ay Seng Hay Project Type Rural Transport 44,542,600
Chranieng 1 202 Laterite road 0.80 [ 0.91 ] Km 46,764,753 4.000 Width (m) 2,620.000 Earth fill m3 42,322,101
Chranieng 2 211 Single pipe culvert 1.00 [ 1.00 ] Place 2,220,552 0.600 Diameter (m) 5.000 Length (m) 2,220,552
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  44,542,653

Baray, Chhuk Khsach

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060107/08/01 TSO Eung Socheat Project Type Rural Transport 46,872,400
Phlov Totueng 1 201 Earth road 0.50 [ 0.37 ] Km 57,108,910 4.000 Width (m) 2,773.060 Earth fill m3 21,016,079
Phlov Totueng 2 211 Single pipe culvert 1.00 [ 1.00 ] Place 1,849,220 0.600 Diameter (m) 5.000 Length (m) 1,849,220
Phlov Totueng 3 223 Triple cell box culvert 1.00 [ 1.00 ] Place 24,007,105 3.000 Total Span (m) 5.500 Width(m) 24,007,105
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  46,872,404

Baray, Chong Doung

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060108/08/01 TSO Eung Socheat Project Type Rural Transport 44,565,300
Samraong 1 202 Laterite road 1.30 [ 1.34 ] Km 33,282,520 4.000 Width (m) 1,780.000 Earth fill m3 44,565,294
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  44,565,294

Baray, Chrolong

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060109/08/01 TSO Ay Seng Hay Project Type Rural Transport 32,601,600
Han Tvear 1 202 Laterite road 0.60 [ 0.55 ] Km 46,441,750 4.000 Width (m) 2,116.000 Earth fill m3 25,751,950
Han Tvear 2 211 Single pipe culvert 1.00 [ 1.00 ] Place 4,447,165 1.000 Diameter (m) 5.000 Length (m) 4,447,165
Han Tvear 3 211 Single pipe culvert 2.00 [ 1.00 ] Place 2,402,545 0.600 Diameter (m) 5.000 Length (m) 2,402,545
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  32,601,660

Baray, Kokir Thum

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060110/08/01 TSO Chhear Nimol Project Type Irrigation 36,553,400
Poun 1 410 Earth dam 0.13 [ 0.13 ] Km 162,214,369 3.000 Max. height (m) 2,646.000 Volume (m3) 21,087,868
Poun 2 420 Canal 0.60 [ 0.60 ] Km 25,775,890 1.200 Depth (m) 2,178.000 Volume (m3) 15,465,534
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  36,553,402

Baray, Krava

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060111/08/01 TSO Chhear Nimol Project Type Irrigation 38,639,700
Roleab 1 420 Canal 0.50 [ 0.50 ] Km 43,774,588 1.200 Depth (m) 3,750.000 Volume (m3) 21,887,294
Pongro Ling 2 455 Single cell box culvert with gate 1.00 [ 1.00 ] Place 16,752,477 1.000 Total span (m) 4.000 Width (m) 16,752,477
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  38,639,771

Baray, Andoung Pou

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060112/08/01 TSO Ay Seng Hay Project Type Rural Transport 33,334,600
Chiveakpheap 1 202 Laterite road 0.71 [ 0.68 ] Km 43,844,962 4.000 Width (m) 2,260.000 Earth fill m3 29,595,349
Chiveakpheap 2 221 Single cell box culvert 1.00 [ 1.00 ] Place 3,739,300 1.000 Total Span (m) 2.100 Width(m) 3,739,300
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  33,334,649

Baray, Pongro

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060113/08/01 TSO Ay Seng Hay Project Type Rural Transport 36,142,700
Pongro 1 202 Laterite road 0.91 [ 0.83 ] Km 43,782,800 4.000 Width (m) 2,302.000 Earth fill m3 36,142,701
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  36,142,701

Baray, Sou Young

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060114/08/01 TSO Ay Seng Hay Project Type Irrigation 35,446,800
Khloy Khang Kaeut 1 410 Earth dam 0.17 [ 0.15 ] Km 146,342,365 1.600 Max. height (m) 1,951.900 Volume (m3) 21,219,643
Khloy Khang Kaeut 2 420 Canal 0.35 [ 0.21 ] Km 14,913,260 0.900 Depth (m) 1,021.000 Volume (m3) 3,124,328
Khloy Khang Kaeut 3 453 Double pipe culvert with gate 1.00 [ 1.00 ] Place 11,102,869 1.000 Diameter (m) 4.000 Width (m) 11,102,869
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  35,446,840

Baray, Sralau

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060115/08/01 TSO Ay Seng Hay Project Type Rural Transport 41,425,600
Kokor 1 202 Laterite road 0.87 [ 0.70 ] Km 49,869,540 4.000 Width (m) 2,890.000 Earth fill m3 34,958,548
Kokor 2 211 Single pipe culvert 1.00 [ 1.00 ] Place 4,222,386 1.000 Diameter (m) 5.000 Length (m) 4,222,386
Kokor 3 211 Single pipe culvert 2.00 [ 1.00 ] Place 2,244,698 0.600 Diameter (m) 5.000 Length (m) 2,244,698
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  41,425,632

Baray, Svay Phleung

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060116/08/01 TSO Ay Seng Hay Project Type Irrigation 32,487,100
Svay Phleung 1 410 Earth dam 0.10 [ 0.09 ] Km 67,048,100 1.300 Max. height (m) 630.000 Volume (m3) 6,268,997
Svay Phleung 2 420 Canal 0.30 [ 0.30 ] Km 8,952,966 0.600 Depth (m) 432.000 Volume (m3) 2,685,890
Svay Phleung 3 452 Single pipe Culvert with gate 2.00 [ 1.00 ] Place 7,420,402 1.000 Diameter (m) 4.000 Width (m) 7,420,402
Svay Phleung 4 452 Single pipe Culvert with gate 3.00 [ 3.00 ] Place 5,370,614 0.600 Diameter (m) 4.000 Width (m) 16,111,842
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  32,487,131

Baray, Tnaot Chum

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060117/08/01 TSO Eung Socheat Project Type Rural Transport 35,230,500
Banteay Chas 1 202 Laterite road 0.80 [ 0.80 ] Km 32,029,768 4.000 Width (m) 560.000 Earth fill m3 25,623,814
Pnov 2 201 Earth road 0.20 [ 0.14 ] Km 66,945,880 4.000 Width (m) 1,406.350 Earth fill m3 9,606,734
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  35,230,548

Baray, Treal

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 060118/08/01 TSO Eung Socheat Project Type Rural Transport 52,945,950
Prey Veaeng 1 202 Laterite road 0.50 [ 0.50 ] Km 34,990,340 4.000 Width (m) 1,326.240 Earth fill m3 17,495,170
Prakhnay 2 202 Laterite road 0.56 [ 0.53 ] Km 67,409,740 4.000 Width (m) 3,137.530 Earth fill m3 35,450,782
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  52,945,952