Sub-project Implementation

Reports / Annual (2007) / Province (24, PLN)

Distrinct
[ #valid contract ]
# Communes # Signed # Abandon Implementation Completed
0 % 30 % 50 % 80 % 90 % 100 %
2401, Pailin [ 4 ] 4 4 0 0 0 0 0 0 0 4
2402, Sala Krau [ 4 ] 4 5 1 0 0 0 0 0 1 3
Total [ 8 ] : 8 9 1 0 0 0 0 0 1 7

# valid contract = [ # signed ] - [ # abandon ]