Sub-project Implementation

Reports / Annual (2007)

Province
[ #valid contract ]
# Communes # Signed # Abandon Implementation Completed
0 % 30 % 50 % 80 % 90 % 100 %
1, Banteay Meanchey [ 44 ] 64 64 20 0 0 0 0 0 0 44
2, Battambang [ 72 ] 96 112 40 0 0 0 0 0 2 70
3, Kampong Cham [ 201 ] 173 216 15 0 0 0 0 0 0 201
4, Kampong Chhnang [ 69 ] 69 71 2 0 0 0 0 0 1 68
5, Kampong Speu [ 80 ] 87 83 3 0 0 0 0 0 0 80
6, Kampong Thom [ 81 ] 81 81 0 6 0 0 0 0 1 74
7, Kampot [ 161 ] 92 161 0 14 0 0 0 0 0 147
8, Kandal [ 159 ] 147 165 6 0 0 0 0 0 2 157
9, Koh Kong [ 48 ] 33 48 0 2 0 1 0 0 13 32
10, Kracheh [ 48 ] 46 55 7 2 0 1 2 0 17 26
11, Mondul Kiri [ 40 ] 21 40 0 2 0 2 0 0 0 36
12, Phnom Penh [ 87 ] 76 87 0 0 0 0 0 0 0 87
13, Preah Vihear [ 31 ] 49 43 12 0 0 0 0 0 0 31
14, Prey Veng [ 108 ] 116 151 43 0 0 1 0 1 13 93
15, Pursat [ 42 ] 49 50 8 0 0 0 0 0 0 42
16, Ratanak Kiri [ 58 ] 49 58 0 14 0 0 0 0 20 24
17, Siem Reap [ 102 ] 100 103 1 0 0 0 0 0 0 102
18, Krong Preah Sihanouk [ 37 ] 22 37 0 2 0 2 0 0 11 22
19, Stung Treng [ 38 ] 34 48 10 0 0 1 0 0 6 31
20, Svay Rieng [ 107 ] 80 144 37 0 0 0 0 0 0 107
21, Takeo [ 104 ] 100 105 1 0 0 0 0 0 26 78
22, Otdar Meanchey [ 25 ] 24 30 5 0 0 0 0 0 1 24
23, Krong Kep [ 7 ] 5 7 0 0 0 0 0 0 3 4
24, Krong Pailin [ 8 ] 8 9 1 0 0 0 0 0 1 7
Total [ 1,757 ] : 1,621 1,968 211 42 0 8 2 1 117 1,587

# valid contract = [ # signed ] - [# abandon]