Sub-project Implementation

Reports / Annual (2008) / Province (01, BMC)

Distrinct
[ #valid contract ]
# Communes # Signed # Abandon Implementation Completed
0 % 30 % 50 % 80 % 90 % 100 %
102, Mongkol Borei [ 15 ] 13 15 0 0 0 0 0 0 4 11
103, Phnum Srok [ 10 ] 6 10 0 0 0 0 0 0 3 7
104, Preah Netr Preah [ 8 ] 8 8 0 0 0 0 0 0 1 7
105, Ou Chrov [ 10 ] 9 10 0 0 0 0 0 0 2 8
106, Serei Saophoan [ 9 ] 8 9 0 0 0 0 0 0 1 8
107, Thma Puok [ 6 ] 6 6 0 0 0 0 0 0 0 6
108, Svay Chek [ 8 ] 8 8 0 0 0 0 0 0 0 8
109, Malai [ 6 ] 6 6 0 0 0 0 0 0 4 2
Total [ 72 ] : 64 72 0 0 0 0 0 0 15 57

# valid contract = [ # signed ] - [ # abandon ]