Sub-project Implementation

Reports / Annual (2008)

Province
[ #valid contract ]
# Communes # Signed # Abandon Implementation Completed
0 % 30 % 50 % 80 % 90 % 100 %
1, Banteay Meanchey [ 72 ] 64 72 0 0 0 0 0 0 15 57
2, Battambang [ 112 ] 96 113 1 0 0 0 0 0 11 101
3, Kampong Cham [ 194 ] 173 196 2 2 0 0 0 0 74 118
4, Kampong Chhnang [ 64 ] 69 64 0 0 0 0 0 0 38 26
5, Kampong Speu [ 83 ] 87 83 0 0 0 0 0 0 0 83
6, Kampong Thom [ 81 ] 81 81 0 0 0 0 0 0 20 61
7, Kampot [ 127 ] 92 127 0 0 0 0 0 0 88 39
8, Kandal [ 138 ] 147 140 2 2 0 0 0 0 53 83
9, Koh Kong [ 39 ] 33 39 0 2 0 1 0 0 35 1
10, Kracheh [ 43 ] 46 43 0 3 0 4 0 1 30 5
11, Mondul Kiri [ 33 ] 21 33 0 3 2 2 1 0 6 19
12, Phnom Penh [ 76 ] 76 76 0 1 1 3 1 0 70 0
13, Preah Vihear [ 42 ] 49 43 1 0 0 0 0 0 0 42
14, Prey Veng [ 151 ] 116 152 1 0 0 0 3 0 58 90
15, Pursat [ 52 ] 49 52 0 2 0 0 0 0 5 45
16, Ratanak Kiri [ 36 ] 49 36 0 2 0 0 0 0 18 16
17, Siem Reap [ 89 ] 100 89 0 7 0 9 0 0 61 12
18, Krong Preah Sihanouk [ 34 ] 22 34 0 0 0 1 0 0 33 0
19, Stung Treng [ 18 ] 29 18 0 1 1 1 0 0 10 5
20, Svay Rieng [ 139 ] 80 144 5 0 0 0 1 0 27 111
21, Takeo [ 97 ] 100 97 0 0 0 1 0 0 37 59
22, Otdar Meanchey [ 24 ] 24 25 1 0 0 0 0 0 18 6
23, Krong Kep [ 5 ] 5 5 0 0 0 0 0 0 5 0
24, Krong Pailin [ 8 ] 8 8 0 0 0 0 0 0 0 8
Total [ 1,757 ] : 1,616 1,770 13 25 4 22 6 1 712 987

# valid contract = [ # signed ] - [# abandon]