Sub-project Implementation

Reports / Annual (2008) / Province (02, BAT)

Distrinct
[ #valid contract ]
# Communes # Signed # Abandon Implementation Completed
0 % 30 % 50 % 80 % 90 % 100 %
201, Banan [ 8 ] 8 8 0 0 0 0 0 0 0 8
202, Thma Koul [ 14 ] 10 14 0 0 0 0 0 0 0 14
203, Battambang [ 18 ] 10 18 0 0 0 0 0 0 1 17
204, Bavel [ 9 ] 6 9 0 0 0 0 0 0 0 9
205, Aek Phnum [ 5 ] 7 5 0 0 0 0 0 0 0 5
206, Moung Ruessei [ 13 ] 11 13 0 0 0 0 0 0 2 11
207, Rotonak Mondol [ 5 ] 4 5 0 0 0 0 0 0 0 5
208, Sangkae [ 10 ] 10 10 0 0 0 0 0 0 0 10
209, Samlout [ 8 ] 7 8 0 0 0 0 0 0 0 8
210, Sampov Lun [ 5 ] 6 6 1 0 0 0 0 0 1 4
211, Phnum Proek [ 5 ] 5 5 0 0 0 0 0 0 4 1
212, Kamrieng [ 6 ] 6 6 0 0 0 0 0 0 3 3
213, Koas Krala [ 6 ] 6 6 0 0 0 0 0 0 0 6
Total [ 112 ] : 96 113 1 0 0 0 0 0 11 101

# valid contract = [ # signed ] - [ # abandon ]