Sub-project Implementation

Reports / Annual (2008) / Province (03, KPC)

Distrinct
[ #valid contract ]
# Communes # Signed # Abandon Implementation Completed
0 % 30 % 50 % 80 % 90 % 100 %
301, Batheay [ 16 ] 12 16 0 0 0 0 0 0 7 9
302, Chamkar Leu [ 11 ] 8 11 0 0 0 0 0 0 8 3
303, Cheung Prey [ 13 ] 10 13 0 0 0 0 0 0 3 10
304, Dambae [ 8 ] 7 8 0 0 0 0 0 0 1 7
305, Kampong Cham [ 5 ] 4 5 0 0 0 0 0 0 0 5
306, Kampong Siem [ 18 ] 15 18 0 1 0 0 0 0 8 9
307, Kang Meas [ 12 ] 11 12 0 0 0 0 0 0 8 4
308, Kaoh Soutin [ 9 ] 8 9 0 0 0 0 0 0 6 3
309, Krouch Chhmar [ 12 ] 12 12 0 0 0 0 0 0 4 8
310, Memot [ 14 ] 14 14 0 0 0 0 0 0 1 13
311, Ou Reang Ov [ 11 ] 7 11 0 0 0 0 0 0 0 11
312, Ponhea Kraek [ 8 ] 8 8 0 0 0 0 0 0 3 5
313, Prey Chhor [ 15 ] 15 15 0 0 0 0 0 0 4 11
314, Srei Santhor [ 14 ] 14 14 0 0 0 0 0 0 8 6
315, Stueng Trang [ 11 ] 12 12 1 0 0 0 0 0 4 7
316, Tboung Khmum [ 17 ] 16 18 1 1 0 0 0 0 9 7
Total [ 194 ] : 173 196 2 2 0 0 0 0 74 118

# valid contract = [ # signed ] - [ # abandon ]