Bidding Summary Report

Location: Kampong Thom \ Kampong Svay Budget Year: 2008

Baray    Kampong Svay    Stueng Saen    Prasat Balangk    Prasat Sambour    Sandan    Santuk    Stoung   

Commune Contract ID Bid Date # Of Bidders # Valid Bidders Qty Changed Award To Contract Value Bidding Detail
Name Bid Value Rejected Note
District: [602] Kampong Svay
Chey 060201/08/01 26-May-2008 5 5 Yes Yi Limcheav [ Yi Limcheav ] 27,377,900 Yi Limcheav [ Yi Limcheav ] 32,535,640 No
Sar Him [ Sar Him ] 33,052,050 No
Eung Sophal [ Eung Sophal ] 33,266,754 No
Sang Naky [ Sang Naky ] 34,182,603 No
Seng Construction [ Choy Pheang ] 34,247,795 No
Damrei Slab 060202/08/01 26-May-2008 4 4 Yes Yi Limcheav [ Yi Limcheav ] 28,655,600 Yi Limcheav [ Yi Limcheav ] 32,579,753 No
Chhang Sarat [ Chhang Sarat ] 32,678,562 No
Sang Naky [ Sang Naky ] 33,038,625 No
Eung Sophal [ Eung Sophal ] 33,228,554 No
Kampong Kou 060203/08/01 26-May-2008 5 5 Yes Sar Him [ Sar Him ] 70,509,300 Sar Him [ Sar Him ] 81,133,795 No
Seng Construction [ Choy Pheang ] 81,847,333 No
Chhey Kim [ Ly Bunheng ] 82,182,879 No
Yi Limcheav [ Yi Limcheav ] 82,540,046 No
Chhang Sarat [ Chhang Sarat ] 82,902,139 No
Kampong Svay 060204/08/01 26-May-2008 5 5 Yes Seng Construction [ Choy Pheang ] 44,456,500 Seng Construction [ Choy Pheang ] 49,226,900 No
Chhang Sarat [ Chhang Sarat ] 49,671,700 No
Chhey Kim [ Ly Bunheng ] 49,683,707 No
Yi Limcheav [ Yi Limcheav ] 50,302,500 No
Eung Sophal [ Eung Sophal ] 50,484,000 No
San Kor 060207/08/01 26-May-2008 4 4 Yes Sang Naky [ Sang Naky ] 50,349,100 Sang Naky [ Sang Naky ] 55,993,067 No
Ngy Try [ Chea Cheak ] 56,514,360 No
Chhey Kim [ Ly Bunheng ] 57,485,171 No
Seng Construction [ Choy Pheang ] 57,485,171 No
Tbaeng 060208/08/01 26-May-2008 4 4 Yes Sang Naky [ Sang Naky ] 45,113,200 Sang Naky [ Sang Naky ] 50,596,018 No
Ngy Try [ Chea Cheak ] 50,717,557 No
Seng Construction [ Choy Pheang ] 51,327,185 No
Yi Limcheav [ Yi Limcheav ] 51,902,440 No
Trapeang Ruessei 060209/08/01 26-May-2008 5 5 Yes Seng Construction [ Choy Pheang ] 52,169,600 Seng Construction [ Choy Pheang ] 54,330,900 No
Chhang Sarat [ Chhang Sarat ] 54,703,180 No
Eung Sophal [ Eung Sophal ] 54,953,900 No
Chhey Kim [ Ly Bunheng ] 55,187,139 No
Yi Limcheav [ Yi Limcheav ] 55,495,500 No

# Of Bidders: number of contractor submit their bid for the specific contract.
# Valid Bidders: number of contractor accepted by the bidding committee.
Rejected: Yes if the bidding committee reject contractor bidding request.