Bidding Summary Report
Location: Kampong Thom \ Stueng Saen Budget Year: 2008
| Commune | Contract ID | Bid Date | # Of Bidders | # Valid Bidders | Qty Changed | Award To | Contract Value | Bidding Detail | |||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Name | Bid Value | Rejected | Note | ||||||||
| District: [603] Stueng Saen | |||||||||||
| Damrei Choan Khla | 060301/08/01 | 12-May-2008 | 5 | 5 | Yes | Chhang Sarat [ Chhang Sarat ] | 37,882,551 | Chhang Sarat [ Chhang Sarat ] | 38,809,185 | No | |
| Seng Construction [ Choy Pheang ] | 39,119,060 | No | |||||||||
| Yi Limcheav [ Yi Limcheav ] | 39,181,997 | No | |||||||||
| Chhey Kim [ Ly Bunheng ] | 39,419,933 | No | |||||||||
| Ngy Try [ Chea Cheak ] | 39,981,798 | No | |||||||||
| Ou Kanthor | 060304/08/01 | 12-May-2008 | 4 | 4 | Yes | Chhang Sarat [ Chhang Sarat ] | 29,216,400 | Chhang Sarat [ Chhang Sarat ] | 32,564,763 | No | |
| Eung Sophal [ Eung Sophal ] | 32,619,329 | No | |||||||||
| MTL [ Ek Proh ] | 33,099,812 | No | |||||||||
| Kao Marin [ Kao Marin ] | 33,129,528 | No | |||||||||
| Kdei Doung | 060305/08/01 | 12-May-2008 | 5 | 5 | Yes | MTL [ Ek Proh ] | 32,030,100 | MTL [ Ek Proh ] | 35,267,143 | No | |
| Chhang Sarat [ Chhang Sarat ] | 35,342,997 | No | |||||||||
| Yi Limcheav [ Yi Limcheav ] | 35,353,024 | No | |||||||||
| Kao Marin [ Kao Marin ] | 37,436,321 | No | |||||||||
| Eung Sophal [ Eung Sophal ] | 37,483,724 | No | |||||||||
| Kampong Krabau | 060306/08/01 | 12-May-2008 | 5 | 5 | Yes | Chhey Kim [ Ly Bunheng ] | 31,252,499 | Chhey Kim [ Ly Bunheng ] | 34,944,648 | No | |
| Eung Sophal [ Eung Sophal ] | 35,123,279 | No | |||||||||
| Ngy Try [ Chea Cheak ] | 35,132,991 | No | |||||||||
| Chhang Sarat [ Chhang Sarat ] | 35,196,922 | No | |||||||||
| Kao Marin [ Kao Marin ] | 35,498,761 | No | |||||||||
| Prey Kuy | 060307/08/01 | 12-May-2008 | 5 | 5 | Yes | Sang Naky [ Sang Naky ] | 31,056,100 | Sang Naky [ Sang Naky ] | 35,363,824 | No | |
| Chhang Sarat [ Chhang Sarat ] | 35,698,186 | No | |||||||||
| Seng Construction [ Choy Pheang ] | 36,063,713 | No | |||||||||
| Chhey Kim [ Ly Bunheng ] | 36,429,111 | No | |||||||||
| Yi Limcheav [ Yi Limcheav ] | 36,906,170 | No | |||||||||
| Prey Ta Hu | 060308/08/01 | 12-May-2008 | 4 | 4 | Yes | Seng Construction [ Choy Pheang ] | 31,050,600 | Seng Construction [ Choy Pheang ] | 32,401,300 | No | |
| Chhang Sarat [ Chhang Sarat ] | 32,869,942 | No | |||||||||
| Sang Naky [ Sang Naky ] | 33,165,259 | No | |||||||||
| Eung Sophal [ Eung Sophal ] | 33,556,217 | No | |||||||||
| achar Leak | 060309/08/01 | 12-May-2008 | 5 | 5 | Yes | Chhang Sarat [ Chhang Sarat ] | 33,575,400 | Chhang Sarat [ Chhang Sarat ] | 33,751,530 | No | |
| Seng Construction [ Choy Pheang ] | 33,873,362 | No | |||||||||
| Sang Naky [ Sang Naky ] | 34,134,089 | No | |||||||||
| Chhey Kim [ Ly Bunheng ] | 34,275,518 | No | |||||||||
| Eung Sophal [ Eung Sophal ] | 34,423,484 | No | |||||||||
| Srayov | 060310/08/01 | 12-May-2008 | 5 | 5 | Yes | Chhang Sarat [ Chhang Sarat ] | 55,760,150 | Chhang Sarat [ Chhang Sarat ] | 60,368,832 | No | |
| Chhey Kim [ Ly Bunheng ] | 61,142,682 | No | |||||||||
| MTL [ Ek Proh ] | 61,352,218 | No | |||||||||
| Yi Limcheav [ Yi Limcheav ] | 61,890,354 | No | |||||||||
| Seng Construction [ Choy Pheang ] | 62,382,171 | No | |||||||||
| Tboung Krapeu | 060311/08/01 | 12-May-2008 | 5 | 5 | Yes | Seng Construction [ Choy Pheang ] | 32,192,450 | Seng Construction [ Choy Pheang ] | 38,176,200 | No | |
| Eung Sophal [ Eung Sophal ] | 38,799,900 | No | |||||||||
| Chhang Sarat [ Chhang Sarat ] | 39,310,009 | No | |||||||||
| MTL [ Ek Proh ] | 39,516,700 | No | |||||||||
| Sang Naky [ Sang Naky ] | 39,974,900 | No | |||||||||
# Of Bidders: number of contractor submit their bid for the specific contract.
# Valid Bidders: number of contractor accepted by the bidding committee.
Rejected: Yes if the bidding committee reject contractor bidding request.