Contract Outputs
Location: Battambang \ Phnum Proek Budget Year: 2005
Banan
Thma Koul
Battambang
Bavel
Aek Phnum
Moung Ruessei
Rotonak Mondol
Sangkae
Samlout
Sampov Lun
Phnum Proek
Kamrieng
Koas Krala
Phnum Proek, Phnum Proek
| Village |
No. |
Code |
Description |
Qty [Contracted] |
Unit |
Dimension #1 |
Dimension #2 |
Total |
| Contract ID |
021101/05/01 |
TSO |
Hul Sina |
Project Type |
Rural Transport |
18,957,000 |
| Phnum Proek |
1 |
203 |
Gravel road |
1.38 [ 1.41 ] |
Km |
12,111,869 |
4.000 Width (m) |
2,641.000 Earth fill m3 |
17,041,400 |
| Phnum Proek |
2 |
211 |
Single pipe culvert |
1.00 [ 1.00 ] |
Place |
1,915,600 |
0.800 Diameter (m) |
5.000 Length (m) |
1,915,600 |
| Note: Qty [Contract] : Planned qty [ qty in contract signed ] |
Grand Total: |
18,957,000 |
Phnum Proek, Pech Chenda
| Village |
No. |
Code |
Description |
Qty [Contracted] |
Unit |
Dimension #1 |
Dimension #2 |
Total |
| Contract ID |
021102/05/01 |
TSO |
Hul Sina |
Project Type |
Rural Transport |
29,752,600 |
| Ou |
1 |
240 |
Concrete bridge (general) |
1.00 [ 1.00 ] |
Place |
29,752,600 |
6.000 |
4.000 |
29,752,600 |
| Note: Qty [Contract] : Planned qty [ qty in contract signed ] |
Grand Total: |
29,752,600 |
Phnum Proek, Chakrei
| Village |
No. |
Code |
Description |
Qty [Contracted] |
Unit |
Dimension #1 |
Dimension #2 |
Total |
| Contract ID |
021103/05/01 |
TSO |
Hul Sina |
Project Type |
Rural Transport |
31,555,900 |
| Tuol |
1 |
203 |
Gravel road |
1.90 [ 1.95 ] |
Km |
14,090,000 |
4.000 Width (m) |
4,044.000 Earth fill m3 |
27,475,500 |
| Tuol |
2 |
211 |
Single pipe culvert |
2.00 [ 2.00 ] |
Place |
2,040,200 |
0.800 Diameter (m) |
5.000 Length (m) |
4,080,400 |
| Note: Qty [Contract] : Planned qty [ qty in contract signed ] |
Grand Total: |
31,555,900 |
Phnum Proek, Barang Thleak
| Village |
No. |
Code |
Description |
Qty [Contracted] |
Unit |
Dimension #1 |
Dimension #2 |
Total |
| Contract ID |
021104/05/01 |
TSO |
Hul Sina |
Project Type |
Rural Transport |
11,202,600 |
| Barang Thleak |
1 |
203 |
Gravel road |
0.77 [ 0.80 ] |
Km |
14,055,960 |
4.000 Width (m) |
3,167.000 Earth fill m3 |
11,202,600 |
| Note: Qty [Contract] : Planned qty [ qty in contract signed ] |
Grand Total: |
11,202,600 |
| Contract ID |
021104/05/02 |
TSO |
Hul Sina |
Project Type |
Rural Transport |
8,150,000 |
| Khvav |
1 |
220 |
Box culvert (general) |
1.00 [ 1.00 ] |
Place |
8,150,000 |
2.000 Total Span (m) |
5.000 Width(m) |
8,150,000 |
| Note: Qty [Contract] : Planned qty [ qty in contract signed ] |
Grand Total: |
8,150,000 |
Phnum Proek, Ou Rumduol
| Village |
No. |
Code |
Description |
Qty [Contracted] |
Unit |
Dimension #1 |
Dimension #2 |
Total |
| Contract ID |
021105/05/01 |
TSO |
Hul Sina |
Project Type |
Rural Transport |
20,739,500 |
| Oulahong |
1 |
240 |
Concrete bridge (general) |
1.00 [ 1.00 ] |
Place |
20,739,500 |
21.000 |
3.500 |
20,739,500 |
| Note: Qty [Contract] : Planned qty [ qty in contract signed ] |
Grand Total: |
20,739,500 |