Contract Outputs

Location: Kampong Cham \ Kampong Cham Budget Year: 2008

Batheay    Chamkar Leu    Cheung Prey    Dambae    Kampong Cham    Kampong Siem    Kang Meas    Kaoh Soutin    Krouch Chhmar    Memot    Ou Reang Ov    Ponhea Kraek    Prey Chhor    Srei Santhor    Stueng Trang    Tboung Khmum   

Kampong Cham, Boeng Kok

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 030501/08/01 TSO Kung mao Project Type Rural Transport 39,132,000
Boeng Kok Muoy 1 201 Earth road 1.36 [ 1.36 ] Km 27,516,129 4.500 Width (m) 3,714.000 Earth fill m3 37,532,000
Boeng Kok Muoy 2 211 Single pipe culvert 1.00 [ 1.00 ] Place 1,600,000 0.600 Diameter (m) 5.000 Length (m) 1,600,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  39,132,000

Kampong Cham, Kampong Cham

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 030502/08/01 TSO Kung mao Project Type Urban Drainage and Flood Protection 41,000,000
Phum Prambei 1 542 Foul water sewer 1.00 [ 1.00 ] Line 14,285,000 0.500 0.000 14,285,000
Phum Prambuon 2 542 Foul water sewer 1.00 [ 1.00 ] Line 18,980,000 0.600 0.000 18,980,000
Phum Dabpram 3 542 Foul water sewer 1.00 [ 1.00 ] Line 7,735,000 0.600 0.000 7,735,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  41,000,000

Kampong Cham, Sambuor Meas

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 030503/08/01 TSO Kung mao Project Type Rural Transport 43,826,000
Boeng Snay 1 201 Earth road 0.97 [ 0.97 ] Km 43,397,739 4.500 Width (m) 1,854.000 Earth fill m3 42,226,000
Boeng Snay 2 211 Single pipe culvert 1.00 [ 1.00 ] Place 1,600,000 0.600 Diameter (m) 6.000 Length (m) 1,600,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  43,826,000

Kampong Cham, Veal Vong

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 030504/08/01 TSO Kung mao Project Type Urban transport 64,421,300
Phum Pir 1 201 Earth road 0.10 [ 0.10 ] Km 71,813,073 4.000 Width (m) 516.000 Earth fill m3 7,181,307
Phum Prammuoy 2 211 Single pipe culvert 1.00 [ 1.00 ] Place 1,800,338 0.600 Diameter (m) 7.000 Length (m) 1,800,338
Phum Buon 3 201 Earth road 0.51 [ 0.51 ] Km 71,813,073 4.000 Width (m) 630.000 Earth fill m3 36,552,854
Phum Prammuoy 4 201 Earth road 0.26 [ 0.26 ] Km 71,813,073 6.200 Width (m) 1,063.000 Earth fill m3 18,886,838
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  64,421,338
Contract ID 030504/08/02 TSO Kung mao Project Type Urban transport 14,100,000
Phum Prammuoy 1 541 Drain pipe for flood water 1.00 [ 1.00 ] Line 14,100,000 89.500 Length (m) 0.600 Diameter (m) 14,100,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  14,100,000