Contract Outputs

Location: Kampong Cham \ Tboung Khmum Budget Year: 2008

Batheay    Chamkar Leu    Cheung Prey    Dambae    Kampong Cham    Kampong Siem    Kang Meas    Kaoh Soutin    Krouch Chhmar    Memot    Ou Reang Ov    Ponhea Kraek    Prey Chhor    Srei Santhor    Stueng Trang    Tboung Khmum   

Tboung Khmum, Anhchaeum

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 031601/08/01 TSO Ven Vorn Project Type Irrigation 49,434,200
Ae Out 1 420 Canal 0.93 [ 0.93 ] Km 36,617,900 1.300 Depth (m) 5,610.000 Volume (m3) 33,981,411
Ponley Phsar 2 420 Canal 0.42 [ 0.42 ] Km 36,617,900 1.300 Depth (m) 3,654.000 Volume (m3) 15,452,754
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  49,434,165

Tboung Khmum, Boeng Pruol

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 031602/08/01 TSO Ven Vorn Project Type Rural Transport 73,000,000
Boeng Kambaor 1 202 Laterite road 1.50 [ 1.50 ] Km 28,947,370 3.500 Width (m) 2,921.000 Earth fill m3 43,421,055
Speam Chheu 2 202 Laterite road 0.40 [ 0.40 ] Km 28,947,370 3.500 Width (m) 790.000 Earth fill m3 11,578,948
Boeng Kambaor 3 222 Double cell box culvert 1.00 [ 1.00 ] Place 17,000,000 3.850 Total Span (m) 4.000 Width(m) 17,000,000
Speam Chheu 4 281 Width restriction posts 1.00 [ 1.00 ] Place 1,000,000 0.400 0.000 1,000,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  73,000,003

Tboung Khmum, Chikor

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 031604/08/01 TSO Doul Son Project Type Irrigation 50,850,000
Slaeng 1 420 Canal 1.50 [ 1.50 ] Km 33,900,000 0.950 Depth (m) 4,835.000 Volume (m3) 50,850,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  50,850,000

Tboung Khmum, Chirou Muoy

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 031605/08/01 TSO Ven Vorn Project Type Rural Transport 38,878,000
Chirou Kraom Muoy 1 202 Laterite road 0.18 [ 0.18 ] Km 27,380,000 3.500 Width (m) 285.000 Earth fill m3 4,873,640
Chirou Leu 2 202 Laterite road 0.95 [ 0.95 ] Km 27,380,000 3.500 Width (m) 677.000 Earth fill m3 26,011,000
Chirou Kandal 3 202 Laterite road 0.25 [ 0.25 ] Km 27,380,000 3.500 Width (m) 242.000 Earth fill m3 6,845,000
Chirou Leu 4 281 Width restriction posts 1.00 [ 1.00 ] Place 1,148,300 4.000 0.000 1,148,300
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  38,877,940

Tboung Khmum, Chirou Pir

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 031606/08/01 TSO Ven Vorn Project Type Rural Transport 48,277,700
Mream Teak 1 201 Earth road 1.07 [ 1.07 ] Km 28,100,000 4.000 Width (m) 2,591.000 Earth fill m3 30,123,200
Tuol Ponley 2 201 Earth road 0.47 [ 0.47 ] Km 28,100,000 4.000 Width (m) 904.000 Earth fill m3 13,207,000
Mream Teak 3 211 Single pipe culvert 1.00 [ 1.00 ] Place 2,473,750 0.600 Diameter (m) 5.000 Length (m) 2,473,750
Tuol Ponley 4 211 Single pipe culvert 1.00 [ 1.00 ] Place 2,473,750 0.600 Diameter (m) 5.000 Length (m) 2,473,750
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  48,277,700

Tboung Khmum, Chob

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 031608/08/01 TSO Doul Son Project Type Rural Transport 52,800,000
Slab Kdaong 1 201 Earth road 0.69 [ 0.69 ] Km 19,200,000 4.000 Width (m) 1,602.000 Earth fill m3 13,248,000
Chrak Chambak 2 201 Earth road 1.26 [ 1.26 ] Km 19,200,000 4.000 Width (m) 2,018.000 Earth fill m3 24,192,000
Tuol Trea Cheung 3 201 Earth road 0.80 [ 0.80 ] Km 19,200,000 4.000 Width (m) 1,281.000 Earth fill m3 15,360,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  52,800,000

Tboung Khmum, Kor

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 031612/08/01 TSO Ven Vorn Project Type Rural Transport 44,366,400
Damnak Popel 1 201 Earth road 0.55 [ 0.55 ] Km 17,064,000 4.000 Width (m) 1,058.000 Earth fill m3 9,385,200
Seh 2 201 Earth road 0.45 [ 0.45 ] Km 17,064,000 4.000 Width (m) 828.000 Earth fill m3 7,678,800
sambuor 3 201 Earth road 1.00 [ 1.00 ] Km 17,064,000 4.000 Width (m) 1,069.000 Earth fill m3 17,064,000
Tep Nimitt 4 201 Earth road 0.60 [ 0.60 ] Km 17,064,000 4.000 Width (m) 714.000 Earth fill m3 10,238,400
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  44,366,400

Tboung Khmum, Lngieng

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 031613/08/01 TSO Ven Vorn Project Type Rural Transport 28,270,200
Lvea Thum 1 201 Earth road 0.71 [ 0.71 ] Km 18,550,000 4.000 Width (m) 1,565.000 Earth fill m3 13,133,400
Khien Chak 2 201 Earth road 0.61 [ 0.61 ] Km 18,550,000 4.000 Width (m) 1,693.000 Earth fill m3 11,296,950
Kokir 3 201 Earth road 0.21 [ 0.21 ] Km 18,550,000 4.000 Width (m) 474.000 Earth fill m3 3,839,850
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  28,270,200

Tboung Khmum, Moung Riev

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 031614/08/01 TSO Doul Son Project Type Rural Transport 41,659,700
Thnong 1 202 Laterite road 1.20 [ 1.20 ] Km 16,166,000 4.000 Width (m) 1,076.000 Earth fill m3 19,318,370
Chi Peang 2 202 Laterite road 0.99 [ 0.99 ] Km 16,165,960 4.000 Width (m) 892.000 Earth fill m3 16,004,300
Trapeang Snao 3 202 Laterite road 0.39 [ 0.39 ] Km 16,166,000 4.000 Width (m) 353.000 Earth fill m3 6,337,072
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  41,659,742

Tboung Khmum, Peam Chileang

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 031615/08/01 TSO Ven Vorn Project Type Rural Transport 41,856,900
Kampong Chanloh Lech 1 202 Laterite road 1.10 [ 1.10 ] Km 31,850,000 3.500 Width (m) 2,453.000 Earth fill m3 35,035,000
Kampong Chanloh Kaeut 2 202 Laterite road 0.17 [ 0.17 ] Km 31,850,000 3.500 Width (m) 289.000 Earth fill m3 5,541,900
Kampong Chanloh Lech 3 281 Width restriction posts 1.00 [ 1.00 ] Place 1,280,000 0.400 0.000 1,280,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  41,856,900

Tboung Khmum, Roka Po Pram

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 031616/08/01 TSO Ven Vorn Project Type Rural Transport 71,142,400
Trapeang Ruessei 1 201 Earth road 1.85 [ 1.85 ] Km 23,384,990 4.000 Width (m) 4,597.000 Earth fill m3 43,145,307
Chong Ou 2 201 Earth road 0.50 [ 0.50 ] Km 23,385,000 4.000 Width (m) 1,288.000 Earth fill m3 11,692,500
Trapeang Ruessei 3 213 Triple pipe culvert 1.00 [ 1.00 ] Place 11,752,600 1.000 Diameter (m) 6.000 Length (m) 11,752,600
Trapeang Ruessei 4 211 Single pipe culvert 1.00 [ 1.00 ] Place 2,276,000 0.600 Diameter (m) 5.000 Length (m) 2,276,000
Chong Ou 5 211 Single pipe culvert 1.00 [ 1.00 ] Place 2,276,000 0.600 Diameter (m) 5.000 Length (m) 2,276,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  71,142,407

Tboung Khmum, Sralab

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 031618/08/01 TSO Ven Vorn Project Type Irrigation 54,810,000
Trapeang Dom 1 420 Canal 0.09 [ 0.09 ] Km 471,000,000 1.600 Depth (m) 7,247.000 Volume (m3) 42,390,000
Trapeang Dom 2 452 Single pipe Culvert with gate 2.00 [ 2.00 ] Place 6,210,000 0.600 Diameter (m) 6.000 Width (m) 12,420,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  54,810,000

Tboung Khmum, Suong

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 031619/08/01 TSO Ven Vorn Project Type Rural Transport 59,502,300
Pou Kel 1 201 Earth road 0.64 [ 0.64 ] Km 24,090,060 4.000 Width (m) 1,629.000 Earth fill m3 15,513,999
Toung 2 201 Earth road 1.83 [ 1.83 ] Km 24,089,980 4.000 Width (m) 3,094.000 Earth fill m3 43,988,303
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  59,502,302

Tboung Khmum, Thma Pechr

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 031621/08/01 TSO Ven Vorn Project Type Rural Transport 46,000,000
Thma Pech Ti Bei 1 201 Earth road 1.66 [ 1.66 ] Km 17,307,690 4.000 Width (m) 3,298.000 Earth fill m3 28,799,996
Thma Pech Ti Bei 2 222 Double cell box culvert 1.00 [ 1.00 ] Place 17,200,000 3.850 Total Span (m) 4.000 Width(m) 17,200,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  45,999,996

Tboung Khmum, Tonle Bet

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 031622/08/01 TSO Ven Vorn Project Type Irrigation 40,231,500
Chrouy Sralau 1 415 Irrigation reservoir 1.00 [ 1.00 ] place 22,472,558 1.300 depth 4,420.000 maximum volume (m3) 22,472,558
Chrouy Sralau 2 452 Single pipe Culvert with gate 2.00 [ 2.00 ] Place 6,200,000 0.600 Diameter (m) 6.000 Width (m) 12,400,000
Chrouy Sralau 3 211 Single pipe culvert 1.00 [ 1.00 ] Place 5,359,000 1.000 Diameter (m) 6.000 Length (m) 5,359,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  40,231,558
Contract ID 031622/08/02 TSO Ven Vorn Project Type Irrigation 20,386,000
Doun Mau Kraom 1 420 Canal 0.66 [ 0.66 ] Km 24,780,500 1.000 Depth (m) 2,153.000 Volume (m3) 16,355,130
Doun Mau Kraom 2 211 Single pipe culvert 1.00 [ 1.00 ] Place 4,030,900 0.600 Diameter (m) 5.000 Length (m) 4,030,900
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  20,386,030

Tboung Khmum, Vihear Luong

Village No. Code Description Qty [Contracted] Unit Dimension #1 Dimension #2 Total
Contract ID 031623/08/01 TSO Ven Vorn Project Type Rural Transport 51,240,000
Thmei 1 201 Earth road 1.20 [ 1.20 ] Km 16,800,000 4.000 Width (m) 1,922.000 Earth fill m3 20,160,000
Cheung Voat 2 201 Earth road 0.45 [ 0.45 ] Km 16,800,000 4.000 Width (m) 721.000 Earth fill m3 7,560,000
Veal Char 3 201 Earth road 0.30 [ 0.30 ] Km 16,800,000 4.000 Width (m) 338.000 Earth fill m3 5,040,000
Prasrae Kraom 4 201 Earth road 1.10 [ 1.10 ] Km 16,800,000 4.000 Width (m) 1,239.000 Earth fill m3 18,480,000
Note: Qty [Contract] : Planned qty [ qty in contract signed ] Grand Total:  51,240,000